We are delighted to inform you that construction work at the College & Mason development is advancing well, and Stage 1 is nearing completion. Here is a comprehensive update on the construction status of each block, along with the anticipated timeline for each stage and information regarding the settlement process.
Stage 1
Lots 21-29 (2 beds) – We are now completing the final external touches, such as fencing and soft landscaping on the 2-bedroom houses. Internal works are complete and final quality reviews are underway.
Lots 8-15 (4 beds) – Final inspections of the 4-bedroom houses have been completed by Auckland Council, and the final touches internally are underway. Prior to completion the internal works will be reviewed by Templeton. Externally, the gardens are now taking shape with fencing being installed and the planting to follow soon after.
Lots 16-20 (3 beds) – Internally, Jennian is adding the finishing touches to the kitchens and flooring, while applying the final coat of paint. Externally, the block has been painted, and main services have been connected. In the upcoming days, the scaffolding will be removed, allowing for the pouring of driveways and the commencement of landscaping.
Lots 30-39 (3 beds) – These homes are nearing completion, slightly behind Lots 16-20. The exterior painting has been successfully finished, and Jennian will soon remove the scaffolding to proceed with pouring the driveways and commencing the hard landscaping at the rear of the properties. Meanwhile, internally, Jennian is adding the final touches to the kitchens and flooring, bringing the overall project closer to its conclusion.
Lots 1-7 (3 beds) – Following the removal of the scaffolding, Jennian has begun the soft and hard landscaping, and the driveways are scheduled to be poured shortly. Internally, the fit-out progress is being carried out simultaneously with the external works, ensuring a coordinated and efficient completion of both the interior and exterior aspects of the project.